How do plug-in solar panels work? What is plug-in solar in the UK?
A plug-in solar kit is one to four solar panels and a small inverter that plugs into an ordinary 13 A socket. The power it makes flows into your home's wiring, and anything switched on uses it before drawing from the grid. People also call it balcony solar. In England, Scotland and Wales the inverter may be rated up to 800 W AC, under rules in force since 27 August 2026.
What is in a plug-in solar kit?
A kit has these parts. Each one has a rule in the product specification that the law points to:
- Solar panels, up to 4 of them. They make direct current (DC), the kind a battery gives.
- A microinverter: a small box that turns the panels' DC into alternating current (AC), the kind your sockets carry.
- Cables ending in a moulded 3-pin plug, fused at 5 A or less, that you cannot open and rewire.
- A mount you can take off again. Cable ties, rope, tape and straps are not allowed as the fixing.
- A label to stick at or near your consumer unit (fuse box), so anyone working on the wiring knows the kit is there.
How does a kit feed power into a socket?
The inverter matches the mains and pushes its power back through the plug into the socket circuit. From there it reaches whatever is running in your home. Those appliances use the kit's power first and take only what is still missing from the grid.
When the kit makes more than your home is using at that moment, the extra flows out through your meter to the network. You are not paid for it by default, so the calculator on this site counts only the power you use at home.
The specification describes this as supplying power "via a plug connection to a final circuit originally designed for electricity import from the grid". That is why it sets rules for the socket:
- Socket circuits only. Not a lighting circuit, and not a spur that feeds fixed equipment such as a cooker or boiler.
- No extension leads, multi-way adaptors, travel adaptors or RCD adaptors.
- An outdoor socket used for the kit must be rated IP55 or better.
- Check your consumer unit has modern residual current protection (RCBOs). With older fuses and no RCBOs, the specification says a professional electrician should check the installation first.
Why the inverter's AC rating is the size that matters
The UK limit is set on the inverter, not the panels. The law covers a kit that "has a maximum rated alternating current output not exceeding 800 watts". The panels may add up to 2,000 W, with no more than 2 in series. So a kit can carry more panel watts than the inverter passes on.
The inverter cannot deliver more than its rating. On a bright day, panel power above it is cut off, which is called clipping. Extra panels still help when the sun is weak and the panels make less than the inverter can take.
An example from this site's data: panels of 400 W on an inverter rated 800 W, on a tilted stand facing south in London. Two panels make about 800 kWh a year. Four panels, twice the panel watts, make about 1,449 kWh: more, but not twice as much. The inverter removes 9% of what the four panels could make.
Above 960 W of panels, the maker must advise you to consider a professional check of your wiring before you install. Kit sizes: 400 W, 600 W and 800 W
Sources: legislation.gov.uk, Department for Energy Security and Net Zero
What do the UK rules allow?
In England, Scotland and Wales, since 27 August 2026, the rules cover a kit with:
- An inverter rated up to 800 W AC.
- Panels adding up to 2,000 W, at most 4 panels and no more than 2 in series.
- A design that meets the Plug-in Solar Device Interim Product Specification and is listed on the Energy Networks Association's Type Test Register before it is sold.
- One kit per household for now. Each flat with its own consumer unit counts as a household.
You tell your network operator when you plug in, no later than 28 days after. The network operator runs the local power lines and is not your energy supplier. You need no approval from it first.
Northern Ireland has not yet made plug-in use lawful. Planning rules, listed building consent and your landlord or freeholder's permission still apply everywhere. Rules last checked 5 October 2026.
The UK rules, one by one · How to tell your network operator · Why Northern Ireland is different
Sources: legislation.gov.uk, Department for Energy Security and Net Zero, Ofgem, Energy Networks Association
What a plug-in kit does not do
- It does not store power. The rules cover solar only. Plug-in batteries and solar-plus-battery kits fall outside the specification, and the instructions must warn that the kit is not meant to be used with a battery. Can you add a battery?
- It is built to stop when the grid supply is lost. The specification calls up BS EN 62116 for anti-islanding, which tests that an inverter stops feeding the wiring when the grid goes down.
- It does not earn export payments by default. The Smart Export Guarantee asks for a certified installation and installer. The government's own impact assessment says it is likely not to apply at first. Why export is not paid
- It does not give you a right to fit one. If you rent, or live in a flat or leasehold home, you need any permission your landlord, freeholder or managing agent requires. Who to ask if you rent or live in a flat
- It is not free of planning rules. England brought plug-in solar into permitted development, but with limits on how far panels stick out and with exclusions, such as listed buildings and timber walls. Plug-in solar planning permission
Sources: legislation.gov.uk, Department for Energy Security and Net Zero, Ofgem
How much does a plug-in kit make in a year?
This site's example kit is 2 panels of 450 W on an inverter rated 800 W. Facing south in London, it makes about 654 kWh a year hung vertically on a railing, and about 900 kWh on a tilted stand.
On a tilted stand, the same kit ranges from 754 kWh a year in Glasgow to 994 kWh in Plymouth, across the 15 UK cities on this site. A railing mount makes about 74% of what a stand makes over a year, but holds up better in winter.
Each figure is a long-term average of 19 years of PVGIS satellite data (2005 to 2023), capped at the inverter's AC rating. It is not a forecast: a real year will be sunnier or duller, and shade from buildings and trees lowers it.
Open the UK calculator · Output by UK city · What it is worth at your rate
What to read next
- Is plug-in solar legal in the UK? Each rule with the source it comes from.
- Do I need to tell my DNO? Who tells the network operator, how and when.
- Socket and circuit checklist What to show an electrician.
- Planning permission Projection limits and exclusions in England, Scotland and Wales.
- Renters, flats and leasehold Who has to say yes before you fit a kit.
- How much can plug-in solar save? kWh and pounds a year at your own rate.
- Output by UK city 15 cities ranked by yearly kWh.
- The UK calculator Your kit, your city, month by month, checked against the limits.
This page gives general information. It cannot tell you that a set-up is safe or lawful in your home: that depends on your wiring, socket, lease and area. When unsure, ask a qualified electrician.
Sources
- Plug-in Solar Device Interim Product Specification, version 2.0 (July 2026), Department for Energy Security and Net Zero.
- The Plugs and Sockets etc. (Safety) Regulations 1994 and Electricity Safety, Quality and Continuity Regulations 2002 (Amendment) Regulations 2026, SI 2026/848, legislation.gov.uk.
- Electricity Safety, Quality and Continuity Regulations 2002, regulation 22, legislation.gov.uk.
- Ofgem decision to approve DCRP/MP/26/02, proposed amendment to facilitate plug-in microgeneration (11 August 2026), Ofgem.
- Who is my electricity network operator?, Energy Networks Association. Read in a browser: the site blocks automated reads.
- Smart Export Guarantee (SEG) for generators; quotes from Ofgem's "SEG: Guidance for Generators" (December 2019), Ofgem. The quotes on this site come from Ofgem's "SEG: Guidance for Generators" (December 2019). No newer plug-in-specific Ofgem statement was found.
- Plug-in solar: final stage impact assessment (DESNZ024(F)-26-CP30), Department for Energy Security and Net Zero.
- The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026, SI 2026/896, legislation.gov.uk.
- PVGIS 5.3 API, non-interactive service, European Commission Joint Research Centre.
Last updated .