You must tell your network operator when you plug in a kit: register before you use it or on the day, and in any case within 28 days. You do it yourself. You need no installer, and no approval from the operator first. This page covers who tells, when, how, and how to find your operator. The limits a kit must meet are on the UK rules page. Last checked 5 October 2026.
Who and when
Who: the householder. The network rules let the customer take the role of installer for a plug-in kit.
When: the regulation says before, or at the time of, commissioning. A 2008 Health and Safety Executive exemption, reproduced in the network rules, allows no later than 28 days after commissioning, counting the day you plug in. Telling the operator on the day you plug in meets both wordings.
Approval: none needed before you connect a single kit under 16 A per phase.
When you stop: you also tell the operator when you remove the kit.
How
The Energy Saving Trust, in a guide written with the Department for Energy Security and Net Zero, sends households to the UK Plug-In Solar Registration website. It says what you need to register and what you get back:
To register your device, you'll need: your name; your postcode; the make and model of the device
Once you've registered, you should get an on-screen confirmation that your device is registered. You won't get an email confirmation of your registration.
The network rules also describe a connect and notify route on the Energy Networks Association's Connect Direct platform. Your kit must come with a statement that notification is mandatory, and a link to instructions on how to do it. Follow the instructions that came with your kit. To check that a model is on the list of devices that meet UK standards, search the ENA Connect Direct device register.
London Fire Brigade gives the same period: Following installation, inform your local Distribution Network Operator (DNO) within 28 days. This helps maintain a balanced electricity network.
Your notification checklist
Enter your kit and the day you plug it in. The checklist gives your last day to register and what to have ready, and prints on one page.
Last day: 28 days counting the day you plug in. Enter the date to see it.
Have ready: your name, your postcode, the make and model of the device.
Where: the UK Plug-In Solar Registration website (myplugin.solar), or the instructions that came with your kit.
Confirmation: on screen only, with no email. Note the date or take a screenshot.
Later: tell the operator again when you remove the kit.
Date registered: ____________________
Which company is your network operator
Your electricity network operator maintains the wires that bring electricity to your home or business. They're different from your energy supplier. Your supplier is the company you pay. The Energy Networks Association has a postcode search for the operator.
What each network operator's website says
Read on 8 October 2026, Electricity North West re-read on 14 October 2026. Of the four operators whose websites could be read, only Electricity North West has a plug-in solar page, and it sends you to the same registration website as above. The other three publish only general routes for small generators, and none of those mentions plug-in kits.
Electricity North West
Its plug-in solar page says: You’re legally required to register any plug-in solar panel devices before you use them in the UK. You can register using the UK plug-in solar website. It also says a kit plugs into a standard socket and that the use of extension cables is not permitted. Its timing is stricter than the regulation's: see below.
UK Power Networks
No plug-in solar page was found. Its Smart Connect service is for installers: Only approved installers can use Smart Connect on behalf of customers.
SP Energy Networks
No plug-in solar page was found. Its general page for a single small generator does not mention plug-in kits.
Scottish and Southern Electricity Networks
No plug-in solar page was found. Its general page for small generators asks for a G98 Form B by email and does not mention plug-in kits.
National Grid Electricity Distribution and Northern Powergrid
Neither website could be read on 8 October 2026: both showed a bot check page instead. This page says nothing about them until they can be read.
What is not confirmed yet
The final text of the network rules (G98 Issue 2 Amendment 1) was not reachable on the date checked, so this page does not name the forms in it. The sources word the timing differently. The Energy Saving Trust says registering is a legal requirement and tells you to register before you use the kit, and Electricity North West says the same. The regulation says before, or at the time of, commissioning, and the exemption allows up to 28 days. Our advice: register before you plug in or on the day, and in any case within 28 days. This site's checks could not open the registration website on the date checked, so this page cannot describe its pages. Follow the link and your kit's instructions.
Engineering Recommendation G98 Issue 2 Amendment 1, consultation draft (June 2026), Energy Networks Association, via dcode.org.uk. The final text was not found online on the checked date. Form names and wording come from the June draft; Ofgem says later changes were limited to clarifications, simpler customer forms, implementation arrangements and minor edits.
ENA Connect Direct LCT device register (plug-in solar devices), Energy Networks Association. The page loads its rows by script from the register's public data feed, so it was read in a browser and from that feed (see docs/research/rules/uk-kit-register-2026-10-03.md).